Pay App Check.

Type your schedule of values. See the nine lines of your G702 and what an owner, architect or lender would send back, before you send it. Free, no account, and nothing you type leaves this page.

Example numbers, not a real job

Schedule of values (G703)

One row per line. Add a change order as its own row and say whether it is signed.

ItemDescriptionScheduled value (C)From previous (D)This period (E)Stored materials (F)Change order?Total to date (G)%Remove
25,000.0062.5%
35,000.00100%
105,000.0070%
60,000.0050%
40,000.0047.06%
8,000.0016%
6,000.0050%
3,000.0046.15%

What a reviewer would see

Likely sent back (2)

  • The schedule of values totals $498,500.00 but the contract sum to date is $492,000.00. These have to be the same number before this goes out.
  • Item CO2 came from a change order that is not executed yet (not signed). Billing unauthorised work is what gets a whole requisition rejected.

Your G702, line by line

1Original contract sum480,000.00
2Net change by change orders (signed only)12,000.00
3Contract sum to date (1 + 2)492,000.00
4Total completed and stored to date282,000.00
5aRetainage on completed work (10%)27,400.00
5bRetainage on stored materials (10%)800.00
5Total retainage28,200.00
6Total earned less retainage (4 minus 5)253,800.00
7Less previous certificates for payment148,500.00
8Current payment due (6 minus 7)105,300.00
9Balance to finish, including retainage (3 minus 6)238,200.00

An arithmetic check against the layout of the AIA G702 and G703 forms, using the same math as the AsBuilt billing desk. Change orders count toward line 2 only when signed. It is not legal or accounting advice; your contract and your owner’s requirements decide what is due. G702 and G703 are documents of the American Institute of Architects; this page is not affiliated with or endorsed by AIA.